For Tier 1/2 supplier quality, process, and project engineers — PFMEA–CP linkage, special characteristics, and executable reaction plans per IATF 16949 customer audits.
Slides use flowcharts and comparison tables; re-brand for internal use. Pairs with the Control Plan article (8.3.2).
3–4 h workshop: case opener → PFMEA mapping table for one operation → worked example → simulated out-of-control reaction.
Align cross-functional teams before trial production; hold production CP approval after trial.
Cross-check PPAP submission lists for document completeness.
Do not copy last product's CP for PPAP; review CP within 48h of PFMEA updates.
Avoid vague reactions like "notify supervisor"; KCC frequencies must not be weaker than PFMEA.
Keep CP, SOP, and inspection spec revisions synchronized.